Overview
New bikeway and multiuse trail along Hennepin Avenue from TH-394 to Lyndale Avenue, terminating at Dunwoody Boulevard. Project adds new asphalt, dedicated bikeways, and improved connectivity for cyclists and pedestrians in central Minneapolis.
Current Status
Status: Construction in progress (2024-2025)
Construction began in 2024 and continued through 2025. Project is actively building new infrastructure along the Hennepin Avenue corridor.
Timeline
- 2024: Construction began
- 2025: Construction continued
- Current: Active construction
- Future: Completion date TBD
Project Scope
Route: Hennepin Avenue (TH-394) → Lyndale Avenue → Dunwoody Boulevard
Key features:
- New asphalt trail surface
- Dedicated bikeways
- Multiuse trail design
- Improved crossings and intersections
- Connection to existing trail network
Importance
This project fills a critical gap in Minneapolis bike infrastructure, creating a continuous north-south connection from TH-394 to Dunwoody Boulevard. The Hennepin-Dunwoody corridor serves high-density areas, improving access for commuters and recreational cyclists.
Monitoring
Tracking items:
- Construction progress and milestones
- Completion date and trail opening
- Intersection and crossing improvements
- Connection to adjacent trails
- City project page updates
External Sources
- City of Minneapolis: Projects — Search for Hennepin-Dunwoody Bikeway
- Minneapolis LIMS — Meeting minutes and project documents